How much rebar for a 30×40 slab?

Short answer

On an example 18 inch grid with 3 inch edges and 24 inch laps, a 30 × 40 ft slab takes about 91 bars of 20 ft rebar (21 bars × 39.5 ft and 28 bars × 29.5 ft). In #4 that is about 1,216 lb of steel, with 588 ties at the crossings.

How to work it out

  1. Bars run inside the edge distance: 39.5 ft × 29.5 ft
  2. Across 29.5 ft at 18 in: 21 bars; along 39.5 ft: 28 bars
  3. 1,796 ft of bar → 91 bars of 20 ft · 0.668 lb/ft = 1,216 lb

A shop or pole-barn slab this size is where rebar counts get interesting, because every run is longer than a 20 ft stick. The 18 in grid and 24 in lap are placeholders to show the math; your plans set both.

Adjust for your project

ft
ft
in
Centre to centre, both ways. This is a structural choice — use the spacing on your plans
in
Bars stop short of the forms; your plans give the cover
Ask your supplier what lengths they stock
in
Only matters when a run is longer than one bar. Your plans or engineer set the lap length
More options: Extra
%
Rebar sticks91 bars#4, 20 ft
Bars in the grid
21 bars × 39.5 ft and 28 bars × 29.5 ft
Total length of bar (incl. laps)
1,796 ft
Weight of the sticks
1,216 lb
Crossings to tie (every one)
588 ties
Chairs at about one per 4 sq ft (check your plans)
292 chairs
  • 70 splices in the grid. Stagger them so they don’t all line up across the slab.
  • Bars must sit inside the concrete, not on the ground: use chairs or dobies at the height your plans show.
Quantity onlyFooting size and depth, reinforcement and slab thickness for structures are set by your local code — check with your building department.

For this job · affiliate link
Rebar cutter and bender91 bars means a lot of cutting and maybe bending. A manual cutter-bender is quieter and makes no sparks or dust compared with a grinder.
View on Amazon (opens in a new tab)

30×40 slab by grid spacing (#4, 20 ft sticks, 24 in laps)

30×40 slab by grid spacing (#4, 20 ft sticks, 24 in laps)
Grid spacing (from your plans)Rebar sticksWeight of the sticksCrossings to tie (every one)
12 in133 bars1,777 lb1,271 ties
16 in102 bars1,363 lb744 ties
18 in91 bars1,216 lb588 ties
24 in69 bars922 lb336 ties

Splices change the count

Runs along the 40 ft side are 39 ft 6 in; along the 30 ft side, 29 ft 6 in. Neither fits in one 20 ft stick. At the 24 in lap used here, two 20 ft bars only reach 38 ft, so each 39.5 ft run takes three bars and two laps (43.5 ft of bar), while each 29.5 ft run takes two bars and one lap (31.5 ft). The laps add about 8% to the steel. Leave the lap at 0 and the calculator warns you, because the count would be short.

There are 21 bars running the length and 28 running the width (the spaces round up so no gap is wider than 18 in), 49 runs in all and about 1,796 ft of bar including laps: 91 sticks of 20 ft, counting each direction’s cut-offs separately. If your supplier stocks 40 ft bars, the long runs fit in one stick each and the count drops; ask, and try the 40 ft option above.

Planning the steel

About 1,216 lb of #4 bar — over half a ton — needs a delivery and a plan for where to stack it. Stagger the splices so they don’t all fall on one line across the slab, tie every crossing, and set the grid on chairs at the height in your plans. The concrete for the same slab is on how much concrete for a 30×40 slab, and the smaller example on how much rebar for a 20×20 slab.

What you’ll need

As an Amazon Associate we earn from qualifying purchases. Links to products are affiliate links — they cost you nothing extra and help keep these calculators free.

Frequently asked questions

How much rebar for a 30×40 slab with 40 ft bars?

About 49 bars of 40 ft (21 bars × 39.5 ft and 28 bars × 29.5 ft).

How much rebar for a 30×40 slab on a 12 inch grid?

About 133 bars of 20 ft #4, roughly 1,777 lb.

Sources