Concrete calculator for slabs, patios and pads
Enter the size and thickness of your slab to see how many cubic yards of concrete to order, or how many bags to buy.
Enter your measurements
More options: Extra · Price
- Or bags of mix (incl. extra)
- 62 bags · 80 lb bag
- Concrete before the extra
- 1.23 cu yd (33.3 cu ft)
- Slab area
- 100 sq ft
- Weight of the concrete (≈ 145 lb/cu ft)
- 4,833 lb (2 tons)
10 ft × 10 ft = 100 sq ft
100 sq ft × 4 in ÷ 12 = 33.3 cu ft ÷ 27 = 1.23 cu yd
+ 10% extra = 1.36 cu yd = 36.7 cu ft
36.7 cu ft ÷ 0.6 cu ft per 80 lb bag = 62 bags
- 62 bags is a lot of mixing. Compare a ready-mix delivery (ask about minimum loads and short-load fees) with the bags vs ready-mix calculator.
- Total to buy counts this as ready-mix. Switch “How will you buy it?” to bags if you are mixing it yourself.
- Plan control joints about 1 in deep every 6–8 ft (Quikrete’s guidance) so shrinkage cracks follow your lines.
Quick answers for common sizes
| Example | Answer |
|---|---|
| How much concrete for a 10×10 slab | 1.36 cu yd with 10% extra (62 bags of 80 lb) |
| How much concrete for a 12×12 slab | 1.96 cu yd with 10% extra (order 2 yd) |
| How much concrete for a 20×20 slab | 5.43 cu yd with 10% extra at 4 in |
| How many yards of concrete for a 24×24 slab | 7.82 cu yd with 10% extra at 4 in |
| How much concrete for a 30×40 slab | 16.3 cu yd with 10% extra at 4 in |
| How many bags of concrete for a 4×4 slab | 10 bags of 80 lb (14 of 60 lb), 4 in thick |
| How many bags of concrete for an 8×8 slab | 40 bags of 80 lb, 4 in thick |
| How much concrete for a 10×12 shed | 1.63 cu yd with 10% extra; about 2 cu yd with a thickened edge |
Your slab at other thicknesses
| Thickness | Concrete to order | Or bags of mix (incl. extra) | Weight of the concrete (≈ 145 lb/cu ft) |
|---|---|---|---|
| 3.5 in | 1.19 cu yd | 54 bags | 4,229 lb |
| 4 in | 1.36 cu yd | 62 bags | 4,833 lb |
| 5 in | 1.7 cu yd | 77 bags | 6,042 lb |
| 6 in | 2.04 cu yd | 92 bags | 7,250 lb |
Concrete is sold by volume: cubic yards from a ready-mix plant (cubic metres outside the US), or bags whose yield is printed on the side. One cubic yard is 27 cubic feet, enough for 81 sq ft of slab at 4 in thick. If you say “cement”, this is still the calculator you want — cement is the powder that binds concrete together, and you buy it already blended with sand and gravel as concrete mix. Cement vs concrete explained.
How to calculate concrete for a slab
Multiply the slab’s area by its thickness to get the volume, convert to cubic yards, then add a little for spillage, form bulge and a base that is a bit low in places. For bags, divide the total by the yield of one bag.
cubic feet = length (ft) × width (ft) × thickness (in) ÷ 12 cubic yards = cubic feet ÷ 27 round slab area = 3.1416 × (diameter ÷ 2)² bags = cubic feet × (1 + extra) ÷ bag yield (cu ft)
A quick check you can do in your head: square feet covered by one cubic yard = 324 ÷ thickness in inches. At 4 in, one yard covers 81 sq ft; at 6 in, 54 sq ft.
| Thickness | Sq ft per cubic yard | Cubic yards per 100 sq ft | 80 lb bags per 100 sq ft |
|---|---|---|---|
| 3½ in (2×4 form) | 92.6 | 1.08 | 48.6 |
| 4 in | 81 | 1.23 | 55.6 |
| 5 in | 64.8 | 1.54 | 69.4 |
| 6 in | 54 | 1.85 | 83.3 |
Worked examples people search for
- How much concrete for a 10×10 slab — the classic patio, and whether bags still make sense.
- How much concrete for a 12×12 slab — almost exactly two yards with the extra.
- How much concrete for a 20×20 slab — a double-garage-sized pad at 4 and 6 inches.
- How many yards of concrete for a 24×24 slab — the common detached garage.
- How much concrete for a 30×40 slab — shops and pole barns, and planning two trucks.
- How many bags of concrete for a 4×4 slab — AC pads and grill pads in 60 and 80 lb bags.
- How many bags of concrete for an 8×8 slab — hot tubs and small shed pads.
- How much concrete for a 10×12 shed — a shed floor, with or without a thickened edge.
Thickness: what the calculator can and can’t tell you
Quikrete’s data sheet says its standard Concrete Mix is for pours 2 in thick or more. Patios, walks and small pads are commonly poured around 4 in. For driveways, garage floors and any slab that carries a building, the thickness — along with any reinforcement and thickened edges — comes from your plans and your local building code, so enter what they specify. The calculator only works out how much concrete that takes.
For driveways and other exterior slabs in freeze-thaw climates, order air-entrained ready-mix: NRMCA’s guide to scaling recommends about 6% air for slabs exposed to freezing and de-icing salt. Standard bagged mixes such as Quikrete’s Concrete Mix don’t list air entrainment on their data sheets, which is one more reason a driveway is a truck job.
Measure what your forms actually give you. A form made from 2×4s set on edge is 3½ in deep, not 4, because a 2×4 is really 1½ × 3½ in. Measure the depth from the top of the form down to the compacted base in several places; a base that dips half an inch in the middle can add 10% or more to the pour.
Do I need rebar or mesh?
Reinforcement doesn’t stop concrete cracking — all slabs crack a little as they shrink and move. What steel and fibers do is hold cracks tight so the pieces stay level, and control joints decide where the cracks go.
- Welded wire mesh — a light steel grid set in the middle of a slab. Often used in patios, walks and shed floors. It has to sit up inside the concrete on chairs to do anything. See the wire mesh calculator.
- Rebar — heavier bars tied in a grid, used where plans call for more strength, such as driveways, garage floors and thickened edges. See the rebar calculator.
- Fibers — synthetic or steel fibers mixed into the concrete (bagged “crack-resistant” mixes, or added by the ready-mix plant). They reduce small shrinkage cracks but don’t replace steel where steel is specified.
Many small 4 in pads are poured with mesh or a fiber mix, and some with neither. For anything carrying a structure, a hot tub or vehicles, ask your building department — and for a shed or spa, the maker’s installation guide — what reinforcement and thickness they require. The calculator counts concrete either way; the steel adds nothing to the order.
How much extra to add
NRMCA’s guide to ordering ready-mix suggests ordering 4–10% more than the volume worked out from the plan dimensions. The calculator starts at 10%:
- 5% — a small slab with straight, braced forms on a level, compacted base.
- 10% — the usual allowance. Covers spillage, a little form bulge and a base that is slightly low.
- 15% or more — uneven or hand-dug ground, or a pour you can’t easily top up if you run short.
Running short is much worse than having a little left over. A slab poured in two parts with a gap between them leaves a weak cold joint, and a second ready-mix delivery can cost far more than the extra concrete would have.
Bags or a truck?
An 80 lb bag makes about 0.6 cu ft, so a cubic yard is 45 bags and about 3,600 lb of dry mix to lift. Up to about a yard, bags and a rented mixer are manageable for two people. Past that, a ready-mix truck is usually less work and gives a more even slab; the bags vs ready-mix calculator compares the two, and the bag yield chart lists every bag size.
Before you pour
- Compact the base and set the forms level (or with the slope you want for drainage). The gravel base calculator sizes the stone under the slab.
- Have enough people and tools ready before the first bag is mixed or the truck arrives. Concrete waits for no one on a hot day.
- Plan control joints. Quikrete recommends cutting them about 1 in deep every 6–8 ft.
- Keep the slab damp, or use a cure-and-seal, for the first several days. See how long concrete takes to cure.
What you’ll need
- Aluminum screedMid-range price
A straight, light screed strikes off the concrete level with the forms. A straight 2×4 works too if it really is straight.
See options on Amazon (opens in a new tab) - Bull float with handleMid-range price
Smooths and levels a slab you can’t reach across, right after screeding. Rent or buy one for anything wider than about 6 ft.
See options on Amazon (opens in a new tab) - Magnesium hand floatBudget price
Closes the surface and pushes stones down after screeding, and prepares the slab for a broom or trowel finish.
See options on Amazon (opens in a new tab) - Concrete edger and groover setBudget price
The edger rounds slab edges so they don’t chip; the groover cuts control joints while the concrete is still soft.
See options on Amazon (opens in a new tab) - Portable electric concrete mixerPremium price
A small drum mixer turns a long day of hand-mixing into batches of two or three 80 lb bags. Check the drum size against the bag count you need.
See options on Amazon (opens in a new tab)
As an Amazon Associate we earn from qualifying purchases. Links to products are affiliate links — they cost you nothing extra and help keep these calculators free.
Frequently asked questions
How many square feet does a yard of concrete cover?
Divide 324 by the thickness in inches: 81 sq ft at 4 in, about 65 sq ft at 5 in and 54 sq ft at 6 in. The yards to square feet calculator works it out for any thickness, and how many square feet a yard of concrete covers shows the common cases.
How do I calculate cubic yards of concrete?
Length (ft) × width (ft) × thickness (in) ÷ 12 gives cubic feet; divide by 27 for cubic yards. A 10 × 10 ft slab 4 in thick is 33.3 cu ft, or 1.23 cubic yards before any extra — see how much concrete for a 10×10 slab.
Should I order exactly what the calculator says?
Order the figure with the extra included, rounded up to what your supplier sells. Ready-mix is usually ordered in fractions of a yard; ask how they round and whether a small order carries a short-load fee.
Does the calculator include rebar or mesh?
No — steel takes up so little of the volume that it doesn’t change the order. Count it separately with the rebar calculator or wire mesh calculator if your plans call for it.
How much does a 4 inch slab weigh per square foot?
About 48 lb per sq ft, at 145 lb per cubic foot — the middle of the 140–150 lb range Iowa DOT gives for normal-weight concrete. The concrete weight calculator handles other sizes.
Related guides
- Concrete and masonry words, explained
- Concrete bag yield chart: 40, 50, 60, 80 and 90 lb bags
- Cement vs concrete: what’s the difference, and which bag to buy
- How to pour a concrete slab: a step-by-step plan with the numbers
- How long does concrete take to cure? Times, temperatures and strength
- Concrete and masonry safety: cement burns, silica dust and heavy bags
Sources
- Quikrete Concrete Mix (No. 1101) data sheet (opens in a new tab) — Yields: 40 lb ≈ 0.30, 50 lb ≈ 0.375, 60 lb ≈ 0.45, 80 lb ≈ 0.60, 90 lb ≈ 0.675 cu ft; unit weight ≈ 140 lb/cu ft; for pours 2 in thick or more; 6–9 pints of water per 80 lb bag; control joints every 6–8 ft; cure 5 days at 70 °F or above, 7 days at 50–70 °F; protect from freezing for 48 hours.
- NRMCA Concrete in Practice 31 — Ordering Ready Mixed Concrete (opens in a new tab) — Truck mixers carry 8 to 12 cubic yards (about 6 to 9 m³); order 4–10% more than the plan estimate; a loaded truck weighs about 80,000 lb; fresh concrete can cause severe chemical burns.
- NRMCA Concrete in Practice 2 — Scaling Concrete Surfaces (opens in a new tab) — Order air-entrained concrete (about 6% air) for exterior slabs exposed to freezing and de-icers; avoid de-icing chemicals in the first winter.
- Iowa DOT Instructional Memorandum 340 — Weight per cubic foot, yield and air content of concrete (opens in a new tab) — Normal-weight concrete is typically 140–150 lb per cu ft at 5 to 8 percent air.
- OSHA 3351 — Preventing Skin Problems from Working with Portland Cement (opens in a new tab) — Wet portland cement can cause caustic burns that may not hurt at first and in severe cases reach the bone.
- NIST Handbook 44, Appendix C — General Tables of Units of Measurement (opens in a new tab) — 1 cubic yard = 27 cubic feet; 1 cubic foot = 1,728 cubic inches.