How much rebar for a 20×20 slab?

Short answer

On an 18 inch grid with bars 3 inches in from the edges, a 20 × 20 ft slab takes 28 bars of 20 ft rebar: 14 bars × 19.5 ft and 14 bars × 19.5 ft. In #4 bar that is about 374 lb of steel and 196 ties at the crossings.

How to work it out

  1. Bars run inside the edge distance: 19.5 ft × 19.5 ft
  2. Across 19.5 ft at 18 in: 14 bars; along 19.5 ft: 14 bars
  3. 546 ft of bar → 28 bars of 20 ft · 0.668 lb/ft = 374 lb

The 18 in grid here is only an example to show the method — your plans or building department set the real spacing and bar size. Change the spacing above and the count updates.

Adjust for your project

ft
ft
in
Centre to centre, both ways. This is a structural choice — use the spacing on your plans
in
Bars stop short of the forms; your plans give the cover
Ask your supplier what lengths they stock
in
Only matters when a run is longer than one bar. Your plans or engineer set the lap length
More options: Extra
%
Rebar sticks28 bars#4, 20 ft
Bars in the grid
14 bars × 19.5 ft and 14 bars × 19.5 ft
Total length of bar (incl. laps)
546 ft
Weight of the sticks
374 lb
Crossings to tie (every one)
196 ties
Chairs at about one per 4 sq ft (check your plans)
96 chairs
  • Bars must sit inside the concrete, not on the ground: use chairs or dobies at the height your plans show.
Quantity onlyFooting size and depth, reinforcement and slab thickness for structures are set by your local code — check with your building department.

For this job · affiliate link
Rebar tie wire and twisterEvery crossing gets a tie so the grid stays put while concrete is placed and walked on. A reel of wire and a twister make it quick.
View on Amazon (opens in a new tab)

20×20 slab by grid spacing (#4, 3 in edges)

20×20 slab by grid spacing (#4, 3 in edges)
Grid spacing (from your plans)Rebar sticksWeight of the sticksCrossings to tie (every one)
12 in42 bars561 lb441 ties
16 in32 bars428 lb256 ties
18 in28 bars374 lb196 ties
24 in22 bars294 lb121 ties

Why the bars fit in single sticks

With the bars stopping 3 in short of each form, every run is 19 ft 6 in — just under a 20 ft stick. That means no splices and very little waste: each bar is a full stick with 6 in cut off. Across 19.5 ft at 18 in spacing there are 14 bars each way (13 spaces of 18 in is 19.5 ft exactly), 28 bars in all.

Tighten the grid to 12 in and it becomes 21 bars each way — 19½ ft doesn’t divide evenly by 12 in, so the count rounds up to keep every gap at 12 in or less — 42 sticks and 441 ties, and the steel weight goes from about 374 lb to 561 lb of #4. Going to #3 bar on the same grid drops the weight by almost half; going to #5 adds more than half again. Those choices are structural, so they come from the plans.

Handling the grid

Twenty-foot sticks are awkward to carry and transport: many yards will cut them in half for a pickup, but then each run needs a splice. If you can, have them delivered full length. Set the grid on chairs at the height the plans call for so it ends up inside the 4 in or thicker slab — see how much concrete for a 20×20 slab for the concrete — and compare how much wire mesh for a slab if your plans allow mesh instead.

What you’ll need

As an Amazon Associate we earn from qualifying purchases. Links to products are affiliate links — they cost you nothing extra and help keep these calculators free.

Frequently asked questions

How much rebar for a 20×20 slab on a 12 inch grid?

42 bars of 20 ft (21 bars × 19.5 ft and 21 bars × 19.5 ft), about 561 lb in #4.

How much rebar for a 20×20 slab on a 24 inch grid?

22 bars of 20 ft, about 294 lb in #4.

How much #3 rebar for a 20×20 slab on an 18 inch grid?

Still 28 bars, but only about 211 lb of steel.

Sources