How much gravel under a concrete slab?

Short answer

A 4 inch compacted base of crusher run under a 10 × 10 ft slab, extended 6 inches past each edge, is 1.49 cubic yards in place. At about 1.9 tons per compacted cubic yard plus 5% waste, order 2.98 tons, about 3 tons.

How to work it out

  1. 11 ft × 11 ft = 121 sq ft × 4 in = 1.49 cu yd compacted
  2. × 1.9 tons per compacted cu yd + 5% = 2.98 tons
  3. Loose, as delivered: 2.98 tons ÷ 1.52 tons/cu yd = 1.96 cu yd

A 10 × 10 slab is the patio, hot-tub pad or shed floor most people start with. The base below it takes nearly as much planning as the concrete and, by weight, almost as much material.

Adjust for your project

ft
ft
in
Use the depth your plans or local practice call for
in
On each side. Some builders run the base a few inches past the forms
More options: Waste
%
Stone to order2.98 tons5,960.37 lb
Compacted volume in place
1.49 cu yd (40.3 cu ft)
Loose volume (as delivered)
1.96 cu yd
Base area
121 sq ft
  • Compact in layers of a few inches with a plate compactor, dampening crusher run so it packs. A soft or wet subgrade under the stone needs fixing first — gravel won’t bridge it.

For this job · affiliate link
Hand tamperA hand tamper handles edges and corners and small pads; for a full slab base, rent a plate compactor for the main area.
View on Amazon (opens in a new tab)

Crusher-run base under a 10×10 slab (6 in overhang) by depth

Crusher-run base under a 10×10 slab (6 in overhang) by depth
Base depth (compacted)Stone to orderCompacted volume in placeLoose volume (as delivered)
2 in1.49 tons0.75 cu yd0.98 cu yd
3 in2.24 tons1.12 cu yd1.47 cu yd
4 in2.98 tons1.49 cu yd1.96 cu yd
6 in4.47 tons2.24 cu yd2.94 cu yd

Why the base is 11 × 11

Running the stone 6 in past every side of the forms gives the slab edges something solid to sit on and keeps the form stakes in firm ground. That turns a 100 sq ft slab into a 121 sq ft base, adding about a fifth to the stone. If your forms sit tight against an existing edge, set the overhang to 0 and the base drops to about 2.46 tons.

In place, 4 in over 121 sq ft is 40.3 cu ft, or 1.49 cubic yards. Crusher run weighs about 1.9 tons per compacted yard (WisDOT gives 1.75–2.1), so the base is 2.84 tons before waste. Delivered loose, it fills about 1.96 yards of truck bed, because it loses a fifth or more of its volume when compacted.

Bulk or bags?

Three tons is a small bulk delivery — many yards have a minimum around that size anyway — and far cheaper than bags. Compact it in two lifts of about 2 in with a rented plate compactor, wetting it lightly so the fines bind. Then build the forms and pour: how much concrete for a 10×10 slab has the concrete, and how many yards of concrete for a 24×24 slab shows a bigger base where a truck delivery is the only sensible option.

What you’ll need

As an Amazon Associate we earn from qualifying purchases. Links to products are affiliate links — they cost you nothing extra and help keep these calculators free.

Frequently asked questions

How much gravel under a 10×10 slab with no overhang?

2.46 tons of crusher run at 4 inches compacted, with 5% extra.

How much #57 stone under a 10×10 slab?

About 2.3 tons at 4 inches with a 6 inch overhang, or 1.79 cubic yards loose.

How much gravel under a 12×12 slab 6 inches deep?

About 6.24 tons of crusher run, base extended 6 inches all round.