How many bags of concrete for a mailbox post?
A 4×4 mailbox post in a 10 inch hole 2 feet deep takes about 1.01 cubic feet of concrete with 10% extra: 3 bags of 50 lb fast-setting mix (2.7 bags exactly) or 2 of 80 lb standard mix.
How to work it out
- Hole 3.1416 × (10 in ÷ 2)² minus the post, × 24 in of concrete
- + 10% = 1.01 cu ft per post ÷ 0.375 cu ft per 50 lb bag = 2.7 bags per post
- One post: buy 3 bags
A mailbox post is a one-post job, which makes fast-setting mix the easy choice: no mixing, and the post stands on its own within the hour. The question is usually how many bags to grab. Slope the top of the concrete away from the post so rain runs off.
Adjust for your project
More options: Gravel · Top · Extra …
- Bags per post
- 2.7 bags
- If you share batches between holes
- 3 bags · 50 lb bag
- Concrete for all posts
- 1.01 cu ft (0.0375 cu yd)
- Quikrete’s rule of thumb for this post
- Hole about 10-1/2 in wide and 24 in deep for a 6 ft post
- Call 811 (in the US) or your local utility locate service a few days before you dig.
Mailbox post in a 10 in hole, by depth
| Hole depth | Bags per post | Concrete for all posts |
|---|---|---|
| 18 in | 2 bags | 0.76 cu ft |
| 24 in | 2.7 bags | 1.01 cu ft |
| 30 in | 3.4 bags | 1.27 cu ft |
| 36 in | 4.1 bags | 1.52 cu ft |
Three bags or two?
At 2 ft deep the hole needs a little over 1 cu ft with a margin. In 50 lb fast-setting bags that is 2.7, so buy 3 — about 150 lb of mix. In 80 lb bags of standard mix it is 1.7, so 2 bags (160 lb), but you have to mix them wet first. Quikrete puts a fast-setting post ready for strain in 4 hours, versus 24 hours for standard mix, which matters when the carrier comes tomorrow.
If you want the top finished in soil or grass, stop the concrete 3–4 in below the surface as Quikrete’s fast-setting instructions describe; at 4 in that trims the concrete by a sixth.
Mailbox post details
Your local post office can tell you the height and setback it wants for the box, and some areas restrict solid masonry or heavy posts near the road because of the risk to vehicles — check before you build anything sturdier than a wood or breakaway post. Call 811 first: the strip along the road often carries buried cables. For a full fence line, see how much concrete for a 4×4 post; a post set on an 8 in tube form instead is on how many bags of concrete for an 8 inch Sonotube.
Different size? Use the full Fence Post Concrete Calculator.
What you’ll need
- Post levelBudget price
Straps to a post or tube form and reads plumb in both directions at once, so you can set it while the concrete is still soft.
See options on Amazon (opens in a new tab) - Post hole diggerMid-range price
Digs neat, straight-sided holes. For more than a dozen holes, rent a powered auger and use this to clean them out.
See options on Amazon (opens in a new tab) - Nitrile-coated work glovesBudget price
Wet concrete and mortar are caustic. Keep the cement off your skin with waterproof gloves, and wash off any that gets in.
See options on Amazon (opens in a new tab)
As an Amazon Associate we earn from qualifying purchases. Links to products are affiliate links — they cost you nothing extra and help keep these calculators free.
Frequently asked questions
How many 80 lb bags of concrete for a mailbox post?
2 bags of 80 lb for a 10 inch hole 2 feet deep.
How much concrete for a mailbox post with a soil cap on top?
About 0.84 cubic feet, 3 bags of 50 lb, stopping 4 inches below the surface.
Other common sizes
- How much concrete for a 4×4 post — 3 bags of 80 lb (or 5 of 50 lb fast-setting) for a 10 in hole 3 ft deep
- How much concrete for a 6×6 post — 4 bags of 80 lb for a 12 in hole 3 ft deep
- How much concrete for a metal fence post — 3 bags of 50 lb fast-setting for an 8 in hole 30 in deep
Sources
- Quikrete Fast-Setting Concrete Mix (No. 1004) data sheet (opens in a new tab) — 50 lb ≈ 0.375 cu ft, 60 lb ≈ 0.45 cu ft, 25 kg ≈ 11.6 L, 30 kg ≈ 14 L; sets in 20–40 minutes; post holes 3× the post width and ⅓ of the post length deep; wait 4 hours before loading a post.
- Quikrete Concrete Mix (No. 1101) data sheet (opens in a new tab) — Yields: 40 lb ≈ 0.30, 50 lb ≈ 0.375, 60 lb ≈ 0.45, 80 lb ≈ 0.60, 90 lb ≈ 0.675 cu ft; unit weight ≈ 140 lb/cu ft; for pours 2 in thick or more; 6–9 pints of water per 80 lb bag; control joints every 6–8 ft; cure 5 days at 70 °F or above, 7 days at 50–70 °F; protect from freezing for 48 hours.
- 811 — Before You Dig (opens in a new tab) — The free national before-you-dig service; contact it a few business days before digging.